The Minister of Power, Prof. Chinedu Nebo, on Wednesday said
there would be more power cuts in the days ahead due to ongoing
maintenance works on installations across the country.
Nebo, while explaining why there was a sharp drop in power supply at a
briefing in Abuja, said the country lost 1,112 megawatts of generated
electricity in two days due to the shutdown of the Chevron gas plant.
He said, “A few days ago, precisely last week Friday, Chevron shut
down its gas plant for maintenance purposes, which was to take place
between Friday and Saturday. And the technical crew in the power sector
knew about the shutdown and this was in order to make sure that damages
are not done before losing the gas entirely.
“From time to time, there is going to be shutdown and it happened two
times recently between Benin and Osogbo. If you don’t shut down these
plants in order to have a safe restarting process, you are going to lose
the equipment. Once routine maintenance is done, the process of
restarting the machines that were shut down takes some time.”
He said two power stations were affected by the recent shutdown,
stressing that the oil company and the ministry’s technicians had to
maintain the plants.
The minister added, “That is why between two and three days, we lost
some 1,112MW. That means Omotoso and Olorunsogo plants were forced to
shut down because there was no gas supply. By design, Chevron has to
maintain the gas pipelines and it was so.
“You will notice that from Monday, we started seeing some increase that has stabilised. Right now, we have over 3,300MW.”
Nebo gave an assurance that occasional system failures would be addressed.
He said, “With regards to occasional system failures, we are in the
process of reviving the huge section of the transmission machinery,
especially the lines that are aged, failing, dilapidated and in need of
replacement. We are working on that.
“And for that reason, whenever a significant part of the transmission
network encounters serious technical problems, you will experience
system shutdown. And whenever you have a serious problem, you must shut
down in order to make sure that the system is not overloaded at one end
and create problems throughout the entire country.”
The PUNCH had exclusively reported on Wednesday that the
nation had witnessed a significant drop in power generation from a peak
of 4,517MW attained on December 21, 2012 to 3,443MW on Tuesday.
The 1,074MW drop is, however, a slight improvement on the 2,987.6MW
peak generation recorded on April 6, 2013, when a whopping 1,529.4MW was
lost.
The minister also said that the meeting with labour unions in the
power sector over workers’ final entitlements had been cordial and that
very soon, private investors would take over the power companies they
bid for.
He also said the issue with Manitoba Hydro International over the
management contract for the Transmission Company of Nigeria had been
resolved, stressing that the transmission infrastructure had received a
boost.
“Manitoba has received the schedule of delegated authority and most issues in the sector have been resolved,” Nebo added.